Friday 7 December 2007 9.00am EST
During the last week Chandra completed the observing schedule as
planned.
A real-time procedure was executed on Dec 4 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer. The schedule of targets for the next week is shown below and includes observations of NCG 1023 coordinated with HST and AEGIS coordinated with Spitzer. |
------------------------------------------
Draco ACIS-S Dec 9
3C332 ACIS-S
3C315 ACIS-S Dec 10
SDSS J133701.39-02 ACIS-S
Radiation Belts
AEGIS-1 ACIS-I
3C 186 ACIS-S Dec 11
NGC2563-P2 ACIS-I
SDSS J074610.50+23 ACIS-S Dec 12
NGC1023 ACIS-S
Radiation Belts
AEGIS-1 ACIS-I Dec 13
074345.47+480813.5 ACIS-S
NGC2563-P5 ACIS-I Dec 14
V1118 Ori ACIS-S
SN 2006gy ACIS-S
Draco ACIS-S Dec 15
Radiation Belts
AEGIS-1 ACIS-I Dec 16
3C197.1 ACIS-S
------------------------------------------
All spacecraft subsystems continued to support nominal operations.
Return to Status Reports