Friday 1 April 2005 9.00am EST
During the last week Chandra completed the observing schedule as
planned.
Of note this week was the completion of a 2 day safemode recovery training simulation held during 28-29 March. The operations team efficiently identified the cause of the simulated safemode and completed a nominal recovery to normal operations mode. The schedule of targets for the next week is shown below. |
------------------------------------------
SDSS J101018.19+00 ACIS-S Apr 3
Crab Nebula (3 obs) ACIS-S/HETG Apr 4
V710 Tau ACIS-S
Maffei 1 ACIS-S
cl0333-2456 ACIS-I Apr 5
MACSJ2219.1-1844 ACIS-I
Radiation Belts
EGS-4 ACIS-I Apr 6
Abell 1569 ACIS-I Apr 7
EGS-4 ACIS-I
cl1312+3900 ACIS-I Apr 8
Radiation Belts
G299.2-2.9 ACIS-S Apr 9
2MASS 031159-46554 ACIS-S
HD 204867 HRC-I
MACSJ1542.0-2915 ACIS-I Apr 10
PSR J1537+1155 ACIS-S
AX J1426.9+2334 ACIS-S
------------------------------------------
All spacecraft subsystems continued to support nominal operations.