News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal (opens in new window)
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Operations CXO Status Report

Wednesday 29 September 1999 8.00am EST

During the last 24 hours the spacecraft was readied for eclipse and radiation belt passage. The SIM was moved to place ACIS in the out-of-focus position and command loads for eclipse and post-belt ACIS CTI measurements were executed. The eclipse was monitored and the spacecraft power systems followed predictions well, as has been the case for previous eclipses. The spacecraft systems continued to operate nominally.

The remaining clean-up actions following safe mode recovery are planned for the morning of 9/28 with fine attitude update. The necessary products were generated and tested overnight. Following fine attitude initialization, a GTO target will be observed until the next radiation passage on 9/29 when the next load will begin.

Analysis from the last radiation belt passage indicates that no further degradation in energy resolution was sustained by the ACIS front-side chips. The back-side chips continue to show no degradation.





Return to Status Reports